UCA Construction Progress Report - November 2010

    Senior Academic Block:
    The structure of the senior academic block is completed while the ceiling work is in progress in the library and laboratory at this block.
    The workers are busy in the ceiling at Laboratory inside senior academic block
       
    The front design of Academic Block A is also under way and will be completed soon
     
    Masjid e Saleem Sarang:
    The structure of the Masjid is already completed while the fixing of tiles is in progress and will be completed soon.
    Pictorial view of Tiles fixed in the basement of Masjid Workers are busy in fixing the tiles inside Masjid at UCA
     
    Picture shows the tiles fixed at the hall of 2nd floor of Masjid.
       
    Hostel 3:
    Ummah welfare Trust (Pak) started the construction of hostel 3 for the orphans of Ummah children academy .In this hostel a total of 400 students will be accommodated. The construction work in the basement is in the final stage. The shuttering is almost completed while work is in progress.
    Top view of hostel 3 as the shuttering work is completed. Picture above and below shows steel fixing in progress.
     

    Written by UWT Pakistan Office.