Construction Report - March/April 2010

    UCA Pakistan Masjid almost complete

    Senior Academic Block B
     
    The structure of academic block B has already been completed, while the plaster work , bricks, plumber, chips grinding, electrical, steel railing, aluminum windows work are also 100% completed.
    Front View of academic block B
    Besides this, 95 % of tile and paint work is also completed. The remaining paint work will be done soon.
    Senior Academic Block C
    The structure of the senior academic block C including bricks, plaster steel railing, wood work, aluminum work are completed. While the plumber, grinding of chips work was completed around 90 %. Finally most of the paint & tile work has been completed.
    The laboratory structure is completed while the finishing remains as UWT (Pak) will import laboratory equipment and tiles from China.
    The laboratory structure is completed while the finishing remains as UWT (Pak) will import laboratory equipment and tiles from China.
    Senior Academic Block A
    The structure of the academic block A including bricks, plumber, electrical, steel railing, wood work has been completed. The structure of the examination hall at block C is complete while the fixing of tiles at the examination hall will be carried out after the purchase of tiles from China. While grinding of chips, aluminum, paint is 90 % completed.
    Beside this the tile work is in the progress at block A which will be completed soon.
    Construction of Masjid in UCA
    The structure of the UCA Masjid including the brickwork is almost complete. While the plaster work is complete on the ground and 1st floor, while plaster work is still in progress on the 2nd floor.
    The construction of the Minar is under way.
    Pictorial view of the Masjid Minar.
    The finishing of the Mehrab remains, which will be completed after the purchase of tiles from China.