    Progress Report of Construction

    Senior Academic Block B
     

    The structure of the Senior Academic Block B is complete. The chip work is also complete in B Block. Tile work is complete on the 1st floor whilst grinding of chips & tile work is also in progress on the last floor as shown in the picture above.
    The worker below is busy cleaning the tiles on the last floor of the Senior Academic Block B. The paintwork is also being carried out at the Academic Block B as shown in the picture above.



    Academic Block C

    The structure of the ground floor of Academic Block C is complete and the work on the shuttering of the 1st floor is in progress. The workers are busy on shuttering on the floor of Academic Block C as the picture shows.

    The brickwork is underway on the ground floor.


                                                                                                     
    Senior Academic Block A
     

    In Academic Block A, the structure of ground floor & 1st floor is complete. Whilst the shuttering & bricks work is in progress on the 2nd floor. The structure of security guards room in front of Academic block A is complete.

    The slab work is done on the ground floor & 1st floor.


     
    Construction of Masjid in UCA

    The shuttering work & the slab work is also complete on the 1st floor of Masjid and the brickwork & shuttering is in progress on the 2nd floor of the Masjid The work on the ablution area & brickwork is also in progress on the 2nd floor of the Masjid.

    The plasterwork is under way on the first floor of the Masjid

                          
                                                                                                                                                      